|
15.1
Power is the lifeline for industrial development of any State. The
creation of new Jharkhand State has thrown a challenge of development of
the state and to bring it to the level of other developed states. The
main intention is to improve the system so that the industries should
get power of right quality, right quantity and one, which is
uninterrupted with constant voltage and frequency at affordable cost.
The State Government will follow the power reforms on the lines of
Central Power Bill – 2001. The objective is also to simplify the
procedures with respect to tariff and other aspects. It is also targeted
to generate power from non-conventional sources.
15.2
The development of power sector is to be given highest priority in the
state’s economic planning to bridge the gap between demand and supply.
The State Government shall encourage the following:
15.2.1 PRIVATE SECTOR PARTICIPATION
The State Government shall encourage Private Sector Participation in
generation and distribution of power. The distribution of power in
industrial areas and major cities of the State like Ranchi, Jamshedpur
and Dhanbad are being contemplated for privatisation. The private sector
power plant would be able to sell power to the State Electricity Board
or to supply directly to bulk consumers and units in their designated
load areas. It shall also be able to sell power to any grid or export
power outside the state with the concurrence of the State Electricity
Board. Thus, it is intended to provide wheeling and banking of power
through the transmission and distribution system of the State
Electricity Board.
15.2.2 CAPTIVE POWER GENERATION
The Government would encourage private sector in setting up of Captive
Power Generation Plants of any capacity to meet the existing as well as
future demand for power of industrial units. For setting up such power
generation unit, no permission from SEB shall be required. The surplus
power generated by such plant could also be purchased by the State
Electricity Board on mutually agreed terms .The State Electricity Board
shall allow wheeling and banking to such power plants . Large industrial
unit / consortium of industrial enterprises in growth centers /
industrial areas shall be allowed to set up power generating units as
well as to take over distribution of power in such industrial complexes
. Such captive power generation and purchase shall be provided exemption
from electricity duty for a period of ten years from the date of
commercial production.
15.2.3 Entrepreneurs will be permitted to use power generating sets. The
unit desirous of using power generating sets shall be required only to
inform the State Electricity Board of their intention in this regard.
15.2.4 PRIORITY TO INDUSTRIAL CONNECTION
To ensure timely starting of industrial project, the State Electricity
Board shall provide LT and H T industrial connection to such units
within a period of 30 and 60 days respectively.
15.2.5 All incentives given to new industrial units shall also be
available to the new power projects.
15.2.6 The Govt. would encourage two-tier tariff system for “peak and
off peak” hour separately. To avail this facility T.O.D. meter shall
have to be installed by the industrial units at their own cost.
15.2.7 The Government shall endeavor to provide exclusive dedicated
feeder to industrial areas to ensure quality, uninterrupted supply of
power to the industrial units located within.
15.2.8 Concept of maximum connected load will be changed to the concept
of maximum Demand Load. Units desirous of availing this facility shall
have to install electronic meters at their own cost.
15.2.9 Industrial units applying for a load of 100 H.P / 100 KVA or less
shall be given connection under LTIS.
15.2.10 Industrial units applying for more than 100 H.P / 100 KVA shall
be given connection under HTIS.
15.2.11 Exemption from payment of Minimum Guarantee Charge for new
Industrial Units having connected load up to 500 KVA or equivalent H.P,
as per billing norms.
15.2.12 For the period the Board is unable to supply power or the
consumers unable to take supply due to certain reasons beyond their
control such as natural calamity, accidental fire, labour unrest, major
industrial accident etc., proportionate relief will be given in fixed
charges and Minimum Guarantee charges.
15.2.13 SEB will accept NSC / Fixed Deposits against security money.
15.2.14 Amount of Security Deposit / Advance shall be fixed on the
basis, on which Minimum Guarantee Charge is calculated and not on the
basis of average consumption.
15.2.15 The rate of delayed payment surcharge shall be recoverable from
the defaulting units at ˝ % (half) interest per week basis and not on
monthly basis.
15.2.16 Notice period for disconnection or reduction of power load by HT
consumers shall be six months.
15.2.17 For H.T. consumers, if the consumption exceeds the contracted
demand up to 15% in a particular month, minimum guarantee charges, fixed
charges, etc. shall be charged extra for that particular month only. On
the other hand if consumption exceeds the contracted demand beyond 15%,
minimum guarantee charges, fixed charges etc. shall be charged extra for
a period of only 6 months instead of present 12 months.
15.3
POWER TARIFF
An independent Electricity Regulatory Commission shall be established by
the Government to rationalise the power tariff and ensure timely
disposal of electricity related disputes between the industrial
consumers and the Board.
15.4
INSTALLED CAPACITY OF POWER IN JHARKHAND
|
Units
|
Type
|
Installed
capacity
|
|
Tenughat
Thermal Power Station
|
Thermal
|
420
MW
|
|
Patratu
Thermal Power Station
|
Thermal
|
840
MW
|
|
Sikkidiri
|
Hydel
|
130
MW
|
|
DVC
|
Thermal/Hydel
|
1200
MW
|
|
Total
|
2590
MW
|
There is immense prospect of capacity addition in both the thermal and
hydel sectors. The Government shall take steps to enhance the capacity
of existing power plants.
15.5
POWER POTENTIAL IN JHARKHAND
There is immense potential for setting up of Thermal, Hydel, Geothermal,
Atomic, Methane and Gas based new power plants in Jharkhand. The
prospects of capacity addition in various power stations is as follows:
|
S. No
|
Unit
|
Type
|
Capacity
|
|
1
|
Patratu
|
Thermal
|
420
MW
|
|
2
|
Tenughat
Vidyut Nigam Ltd. Phase I
|
“
|
630
MW
|
|
3
|
Tenughat
Vidyut Nigam Ltd Phase II
|
“
|
500
MW
|
|
4
|
Chandil
|
“
|
500
MW
|
|
5
|
North
Karanpura
|
“
|
2000
MW
|
|
6
|
Shankh
II
|
Hydel
|
186
MW
|
|
7
|
Tilaiya
Dhadhar
|
“
|
50
MW
|
|
8
|
Kanhar
|
“
|
450
MW
|
|
|
Total
|
4736
MW
|
15.6
Besides, a number of mini and micro hydel power plants can also be
installed at various identified localities, each of which may provide 1
MW power to 10 MW to the adjacent localities. The Government shall
accord “Industry Status” to such mini / micro power generating units
which would be allowed to wheel energy.
15.7
Private sector would also be encouraged to exploit and develop
non-conventional sources of power, such as geothermal energy, biomass
based power, solar power, wind power etc. to generate power locally and
provide it in the remote areas. The Government shall accord “Industrial
Status” to such non-conventional sources of power generating units,
which also would be allowed to wheel energy.
15.8
RURAL
ELECTRIFICATION
The State Government has undertaken
massive rural electrification programme to provide electricity to all
villages and rural areas. The investment being made for this purpose is
Rs. 30 crores in the current year 2001-2002.
|